Integration engineering, procurement and consultation for the Grand Renewable Energy Park
Norda Stelo provides technical support to Samsung C&T in integration engineering, procurement and consulting services for the Grand Renewable Energy Park project. Samsung C&T, in partnership with Korea Power Electric Corporation and Pattern Energy, has conducted the development, construction and operation of the park.
Highlights
- Engineering, procurement and construction management (EPCM) and monitoring for the 275 MW Grand Renewable Energy Park project, including wind and solar facilities
- 67 wind turbines
- 425,000 photovoltaic solar panels
- Collector substation, interconnection station, operations and maintenance building
- 82 km of new 34.5 kV overhead and/or ground lines for the collector system
- 45 km of access roads to the wind turbines
Related projects
-
Environmental impact assessment for the Toulnustouc hydroelectric plant project
-
Construction of the spillway for the new Péribonka IV power plant
-
Multiple electrical engineering projects for an industry leader in the Middle East and North Africa
-
Engineering and technical assistance for electric power line installation