Seymour Falls Dam Spillway Gate - Norda Stelo
Seymour Falls Dam Spillway Gate

Seymour Falls Dam Spillway Gate

Norda Stelo designed a new hydraulically actuated spillway gate for Seymour Falls Dam, whose reservoir supplies approximately one-third of Metro Vancouver’s drinking water. The project aimed to improve operational safety, provide greater flexibility for annual fish migration, and integrate the new gate into the existing spillway while minimizing impacts on reservoir operations.  

Seymour Falls Dam Spillway Gate

LOCATION
North Vancouver, British Columbia, Canada

CLIENT
Metro Vancouver

01
The challenge

Seymour Falls Dam impounds a reservoir that supplies approximately one-third of Metro Vancouver’s drinking water. The new gate had to be installed while maintaining reservoir operations and protecting both a sensitive environment and a critical regional water supply. The gate’s location complicated the coordination of construction activities and limited personnel access, which had to be closely monitored. 

The gate also had to fit the geometry of a spillway built in the early 1960s. Its custom design required careful detailing of the seals, attachment to the heavily reinforced concrete structure, and a leak-free fit with the existing spillway. 

02
Our approach

Norda Stelo developed a custom hydraulic gate concept tailored to the existing spillway. The solution incorporated environmentally friendly hydraulic fluid, access to hoisting equipment from the bridge deck level, easy attachment to the spillway, seismic isolation from the bridge deck, and vertical installation and operation. 

The team worked with the contractor’s surveyors and used 3D laser scanning and 3D modeling to adjust the design drawings and ensure an accurate, leak-free fit between the new gate and the existing spillway.  

03
The result

The new gate provides greater flexibility for annual fish migration. It also improves operational safety by reducing the need for workers to access the reservoir and spillway areas. 

The solution successfully integrated the new gate into an existing spillway structure built in the early 1960s while maintaining reservoir operations. Coordination among Metro Vancouver, the contractor and the design team minimized the required shutdown time and reduced the capital cost. 

04
Highlights
  • All the specific elements of the project that deserve to be mentioned. (Innovations, extraordinary elements, unique or ingenious solutions, etc.). 
  • Design of a hydraulically actuated spillway gate integrated into an existing structure built in the early 1960s. 
  • Use of 3D laser scanning and 3D modeling to achieve an accurate, leak-free fit. 
  • Use of environmentally friendly hydraulic fluid. 
  • Seismic isolation of the gate from the bridge deck. 
05
Key expertise
  • Electrical
  • Mechanical
  • Structural
Projects
Other projects that might interest you

Discover some of our most representative projects, showcasing our expertise and experience in engineering.

Energy

Cleveland Dam Airshaft Service Elevator and Ducting System

Metro Vancouver retained Norda Stelo as the Prime Consultant for the design and installation of a new service elevator and ducting system within an existing 60-metre-deep airshaft at Cleveland Dam. The project aimed to improve safe access to the underground galleries while protecting the equipment from the effects of a wet environment prone to icing.
Energy

La Romaine Hydroelectric Complex Access Road

As part of the development of the approximately 1,500-megawatt (MW) Romaine Hydroelectric Complex, Norda Stelo contributed to the design of an access road connecting Highway 138 to the project’s various facilities. This approximately 150 km road corridor extends through a remote northern environment and provides access to generating stations, dams, dikes, camps and other infrastructure. The mandate included route studies, technical surveys, detailed engineering, plans and specifications, clearing studies, as well as technical assistance during construction.